How Long Does a Kitchen Remodel Take in Franklin, WI?
If you’re planning a kitchen remodel in Franklin, the first question is almost always the same: how long is this going to take? After decades in the remodeling industry, the honest answer is that most full kitchen remodels take three to six months from the first conversation to the final walkthrough. The actual construction, the part where your kitchen is torn apart, usually runs four to eight weeks.
That gap surprises a lot of homeowners. Much of a remodel happens before anyone swings a hammer: designing the layout, choosing materials, and waiting for cabinets to be built. Knowing what each phase involves, and what can slow it down, makes the whole process far less stressful.
Here’s what to expect, phase by phase, for a kitchen remodel in Franklin and the surrounding Southeast Wisconsin area.
Standard Kitchen Remodel Timeline at a Glance
| Phase | Typical time | What happens |
|---|---|---|
| Consultation and measurements | 1 to 2 weeks | In-home visit, measurements, goals and budget |
| Quote and signed contract | 1 to 2 weeks | Detailed quote, signed contract, deposit |
| Selections | 1 to 3 weeks | Cabinets, countertops, tile, flooring, fixtures |
| Design | 1 to 3 weeks | Floor plan, cabinet layout, renderings, revisions |
| Ordering and lead times | 4 to 12 weeks | Cabinets and materials are built and delivered |
| Demolition | 1 to 3 days | Old kitchen comes out |
| Rough-in and inspections | 1 to 2 weeks | Plumbing, electrical, framing, city inspections |
| Drywall, paint and flooring | 1 to 2 weeks | Walls closed up and finished |
| Cabinet installation | 2 to 5 days | Cabinets set and leveled |
| Countertops | 1 to 3 weeks | Template, fabrication, install |
| Backsplash and finishing | 1 to 2 weeks | Tile, sink, appliances, lighting, hardware |
| Final walkthrough | A few days to 1 week | Punch list and final touches |
| Total | About 3 to 6 months from first visit to finished kitchen, with 4 to 8 weeks of construction | |
The Kitchen Remodel Process
Phase 1: Consultation and Measurements (1 to 2 weeks)
Everything starts with a visit to your home. A good remodeler will look at the space, take detailed measurements, and ask how you actually use your kitchen. Who cooks? Do the kids do homework at the island? Do you entertain often? Those answers shape the design far more than any trend.
This is also when you’ll talk through budget and scope. Are you keeping the current layout, or moving the sink, range or walls? That single decision affects the timeline more than almost anything else.

Phase 2: Quote and Signed Contract (1 to 2 weeks)
After the consultation, you’ll receive a detailed quote based on your goals, measurements and budget. Take the time to review it and ask questions. Once the contract is signed and the deposit is in, the project is officially on the schedule.
Phase 3: Selections (1 to 3 weeks)
This is the fun part, and it’s also where projects most often stall. You’ll choose cabinet style and finish, countertops, backsplash, flooring, hardware, sinks, faucets and lighting. Homeowners who come in with inspiration photos and a clear sense of their style tend to move through this quickly. Those who second-guess every choice can add weeks.
Phase 4: Design (1 to 3 weeks)
With your selections made, the design comes together. You’ll see a floor plan, cabinet layout and often 3D renderings showing your chosen cabinets, countertops and finishes in your actual space. This is your chance to review everything and request changes before anything is ordered.
Phase 5: Ordering and Lead Times (4 to 12 weeks)
Once the design is approved, materials are ordered. Cabinets are almost always the longest wait. Semi-custom and custom cabinetry is built to order and commonly takes six to ten weeks to arrive. Special-order tile, appliances and fixtures can have their own delays.
An experienced remodeler won’t start demolition until the cabinets have arrived or have a confirmed delivery date. It’s tempting to want to start sooner, but tearing out a kitchen and then waiting on materials means weeks without a working kitchen for no reason.
Phase 6: Demolition (1 to 3 days)
The old cabinets, countertops, flooring and anything else being replaced come out. Floors and nearby rooms are protected, and dust barriers go up. This is also when hidden problems show up, which we’ll cover below.
Phase 7: Rough-In Work and Inspections (1 to 2 weeks)
Plumbing, electrical, ductwork and any framing changes happen behind the walls now. If you’re adding recessed lighting, moving the sink or adding outlets to the island, it’s done here. In Franklin, work like this typically requires permits and inspections through the city before the walls can be closed up.
Phase 8: Drywall, Paint and Flooring (1 to 2 weeks)
Walls are patched or replaced, primed and painted. Depending on the flooring material and the plan, floors may go in before or after the cabinets.
Phase 9: Cabinet Installation (2 to 5 days)
This is when it starts to look like a kitchen again. Cabinets are set, leveled and secured, and the layout you’ve been looking at in renderings becomes real.
Phase 10: Countertops (1 to 3 weeks)
Stone countertops can’t be measured until the cabinets are installed. The fabricator creates a precise template, then cuts and finishes the slabs. Installation itself takes a day, but the wait between templating and install is commonly one to two weeks.
Phase 11: Backsplash, Fixtures and Finishing (1 to 2 weeks)
With countertops in, the backsplash is tiled, the sink and faucet are connected, appliances go in, lighting is finished, and hardware is installed.
Phase 12: Final Walkthrough and Punch List (a few days to 1 week)
You’ll walk the finished kitchen with your remodeler and note anything that needs attention: a door that needs adjusting, a scuff on the paint, a missing piece of trim. A quality remodeler takes this step seriously. It’s the difference between a kitchen that’s done and a kitchen that’s done right.
What Can Affect Your Kitchen Remodel Timeline
Every kitchen is different, but the same handful of factors cause most delays.
Cabinet lead times. Cabinets set the pace for the whole project. Stock cabinets ship quickly, while semi-custom and custom lines are built to order. If you have a firm deadline, like hosting the holidays, talk about it before you choose a cabinet line.
Layout changes. Keeping the sink, range and refrigerator where they are is the fastest path. Moving plumbing, gas lines or walls adds rough-in time, inspections and sometimes structural work.
Permits and inspections. Most kitchen remodels involving electrical, plumbing or structural changes require permits through the City of Franklin. An experienced remodeler builds inspection time into the schedule, so the work keeps moving instead of sitting idle.
Surprises behind the walls. Many Franklin homes were built decades ago, and opening the walls can reveal outdated wiring, old plumbing, water damage or uneven subfloors. These are better fixed now than covered up, but they can add days or weeks.
Wisconsin seasons. Interior work happens year-round, but winter weather can slow deliveries, and spring and early summer are the busiest time of year for remodelers. Starting your planning in fall or winter often means a better spot on the schedule.
Decision-making. Changes after materials are ordered, or slow decisions during selections, are among the most common causes of delay. The more decided you are up front, the smoother the project goes.

Living Through a Kitchen Remodel
Four to eight weeks without a kitchen is manageable with a little planning. Families who set up a temporary kitchen ahead of time almost always have an easier experience.
- Pick a spot. A dining room, basement or laundry room works well. You’ll want an outlet or two and, ideally, a nearby sink.
- Keep the essentials. A microwave, coffee maker, toaster oven or air fryer, and a mini fridge cover most meals.
- Pack early. Box up everything in your cabinets a week or two before demolition, and keep out only what you’ll actually use.
- Plan simple meals. Grilling, slow cooker meals and some takeout get most Franklin families through just fine. Paper plates save a lot of dishwashing in the bathroom sink.
- Expect some dust and noise. A good crew contains it as much as possible, but demolition days will be loud.
How to Keep Your Kitchen Remodel on Schedule
- Start planning early. If you want your kitchen done by a certain date, start the conversation four to six months ahead.
- Gather inspiration first. Save photos from Pinterest, Houzz or Instagram of kitchens you love. It speeds up both design and selections.
- Set a realistic budget up front. Knowing your range helps your remodeler guide you toward materials that fit, which avoids redesigns later.
- Make decisions and stick with them. Changes after ordering are one of the biggest sources of delay and added cost.
- Plan for a contingency. Setting aside 10 to 15 percent for surprises, especially in older homes, keeps a hidden problem from stopping the project.
- Choose an experienced, local remodeler. A contractor who regularly works in Franklin knows the permit process, has reliable trade partners, and schedules the work so crews aren’t waiting on each other.
- Stay in communication. Respond to questions quickly and ask for regular updates. Small delays in answers can turn into bigger delays on site.
Frequently Asked Questions
How long does a kitchen remodel take in Franklin, WI?
Most full kitchen remodels take three to six months from first consultation to completion. Construction itself usually takes four to eight weeks. Smaller updates, like new countertops and backsplash only, can be finished in a couple of weeks.
What takes the longest in a kitchen remodel?
Waiting on cabinets. Semi-custom and custom cabinets are built to order and commonly take six to ten weeks to arrive, which is why ordering happens well before demolition.
Do I need a permit for a kitchen remodel in Franklin?
If the project involves electrical, plumbing, gas or structural changes, a permit is typically required through the City of Franklin. Cosmetic updates may not need one. Your remodeler should handle the permit process for you.
Can I live in my home during a kitchen remodel?
Yes. Most homeowners stay in the house and set up a temporary kitchen in another room. Expect some dust and noise, especially during demolition.
What’s the best time of year to remodel a kitchen in Wisconsin?
Interior remodeling happens year-round. Planning in the fall or winter often helps you get on a remodeler’s schedule before the busy spring and summer season.
Why can’t demolition start right after I sign?
A well-run project waits until materials, especially cabinets, are on hand or have firm delivery dates. Starting too early can leave you without a kitchen for weeks while nothing is happening.

Ready to Plan Your Franklin Kitchen Remodel?
A kitchen remodel is a big project, but it doesn’t have to be a stressful one. Knowing what to expect at each phase, planning ahead for lead times, and working with an experienced local team makes all the difference. Done right, it’s an investment you’ll enjoy every day for decades.
If you’re thinking about remodeling your kitchen in Franklin or anywhere in Southeast Wisconsin, Wisconsin Kitchen Remodeling can connect you with a trusted local remodeler. Fill out our form to get started and take the first step toward the kitchen you’ve been picturing.
Keep Reading
How to Choose Cabinet Door Styles for Your Kitchen
Shaker, slab, inset or raised panel? Here’s how the most popular cabinet door styles compare and which ones fit your home, from craftsman to contemporary.
Quartz vs. Quartzite vs. Granite: Choosing the Right Kitchen Countertop
Quartz, quartzite or granite? Compare how each countertop looks, holds up and costs so you can choose the right fit for your kitchen and the way you use it.
Stock vs. Semi-Custom Cabinets: Why Semi-Custom Is Worth It
Stock or semi-custom? Here’s how the two really compare and why semi-custom cabinets give you a better fit, better quality and a kitchen that lasts.